Red Deer Wastewater borgata poker room Plant – Phase 3 Upgrades
Location: Red Deer, AB
The process systems for the project included: one UV disinfection system complete with two UV banks; one new Single Stage Aeration Blower; five Secondary Clarifier Mechanisms (one in a new tank, four in existing tanks); seven new Centrifugal RAS Pumps; two new Severe Duty Progressive Cavity WAS Pumps; two new Horizontal Chopper Scum Pumps; two Vertical Turbine Pumps for Service Water; four new Submersible Horizontal Propeller Mixers; one new Fine Bubble Aeration System; and one new Escalator fine Screen.
This project used the conventional three stage sewage borgata poker room process, and was completed within the required timeframe. It was also completed for one million dollars under the original contract budget.
Contract Value
M CAD
Prime Consultant
Stantec
Project Owner
City of Red Deer
Contract Format
Stipulated Price
Completion Date
Nov 2009
Contract Duration
29 Months