Keswick borgata online casino reviews Pollution Control Plant Expansion
Location: Georgina, ON
The project consisted of borgata online casino reviews of the following structures and their related equipment: a new headworks building, including two vortex grit removal chambers; a new generator building and substation; a new aeration tank; two new secondary clarifiers; a new RAS/WAS pumping station; a new Microscreening (reverse osmosis filtration) and UV treatment building; a new odour control biofilter; upgrades to the equipment in the existing aeration tanks; upgrades to the equipment in the existing clarifiers; modifications to the existing administration building, including removal of the existing chlorine facility; and modifications to the existing sludge handling facility.
The borgata online casino reviews was carried out in multiple stages to ensure that the operations of the existing plant were uninterrupted; ensuring that borgata online casino reviews did not impact the quality of the discharged water.
Contract Value
M CAD
Prime Consultant
Hatch Mott Macdonald
Project Owner
Regional Municipality of York
Contract Format
Stipulated Price
Completion Date
Sep 2014
Contract Duration
42 months