borgata poker room Main Works Yard
Location: borgata poker room, British Columbia
This project completely reconfigured and densified the City of borgata poker room’s existing Operations Centre and Works Yard site to provide a new Operations Centre and Fleet Maintenance Facility.
The scope of work consisted of three main buildings including a four-storey Operations Centre/Administration Building with a single storey workshop, a Fleet Maintenance Building and Warehouse including vehicle maintenance bays, repair shops and office space as well as three pre-engineered structures including a Decant Facility and two Storage Buildings providing general storage and loading space. The project also included space for fleet parking, storage, social gathering, loading, and off-site works.
borgata poker room was executed in phases since it was critical to maintain uninterrupted facility operations. Overall schedule was met, finishing the final phases slightly before the original scheduled completion date. The facility has achieved LEED Silver Certification and is to be 40% more energy efficient than a typical Operations Building.
Contract Value
million
Prime Consultant
Taylor Kurtz Architecture Design
Project Owner
City of borgata poker room
Contract Format
borgata poker room Management
Completion Date
September 2016
Contract Duration
40 months